Run chart is used to understand the trends in a process or
variation over time. Here I am making run chart for total production/shift of
any components/items for a week.
Step1: Collect the data and enter it as shown below:
Step2: Make column ‘C’ for Average by using the formula (AVERAGE
(B2:B13)) as shown below :
Step3: Now select A1:A13, B1:B13, C1:C13 as shown in fig.
then go to insert tab and select line option as shown below:
Finally run chart will prepare and look like as below: